If you’ve ever installed solar panels, you’ve probably asked: "How many days does it take to review the photovoltaic panels installed on site?" Spoiler alert: It’s like asking how long it takes to bake a cake without knowing the recipe. But don’t panic—we’re breaking down the variables, surprises, and secret hacks to avoid getting stuck in permit purgatory.
Contact online >>
If you’ve ever installed solar panels, you’ve probably asked: "How many days does it take to review the photovoltaic panels installed on site?" Spoiler alert: It’s like asking how long it takes to bake a cake without knowing the recipe. But don’t panic—we’re breaking down the variables, surprises, and secret hacks to avoid getting stuck in permit purgatory.
Local governments and utilities don’t exactly roll out a red carpet for your shiny new PV system. The review timeline depends on three key ingredients:
In sunny California, streamlined cities like San Diego approve residential systems in 7-10 business days. Meanwhile, smaller towns with understaffed offices might take 4-8 weeks. A 2023 Solar Energy Industries Association (SEIA) report found:
Submitting outdated NEC (National Electrical Code) compliance docs? That’s like bringing a flip phone to a ChatGPT party. One installer shared a horror story where a single missing signature added 14 days to their review. Pro tip: Triple-check interconnection agreements and shading diagrams.
Authority Having Jurisdiction (AHJ) reviewers aren’t robots. One might greenlight a system in a day; another could nitpick conduit spacing for weeks. A Florida project sailed through in 5 days while the same design took 27 days in Texas. Why? Blame local amendments to fire codes.
Online portals sound efficient—until your application gets lost in digital limbo. A Massachusetts developer recently waited 11 days just for a portal password reset. Always call to confirm submission receipt!
File during "solar rush" seasons (spring/fall), and you’re competing with every Tom, Dick, and Harry’s installation. One Colorado utility’s review time ballooned from 12 days to 38 days during Q2 2024. Moral: Schedule submissions during off-peak months.
Many cities now offer solar-specific checklists. For example, Phoenix’s "SolarONE" program guarantees 10-day reviews if you follow their 23-step guide. Skip a step? Back to the end of the line!
Third-party expeditors who know inspectors by name can work magic. A Nevada firm slashed a 45-day timeline to 9 days by:
SolarAPP+ (Solar Automated Permit Processing) is shaking things up. Adopters like Tucson saw review times drop by 70%. The software:
A New York installer shared their "4-Week Review Nightmare" at a recent SPI conference:
Their takeaway? "Assume the review will take twice as long as they say. Then add a margarita fund to your project budget."
Emerging trends that could make "how many days" questions obsolete:
So next time someone asks about photovoltaic panel review timelines, tell them: "Anywhere from the time it takes to drink a latte to growing a decent beard. But hey, at least it’s not 2005 anymore!"